How long will it take Southern Belt Construction and Remodeling to do your Houston home’s kitchen remodeling project? The answer is dependent on a number of criteria, including the size of your kitchen, the materials you want to use, and the scope of the remodeling. If you have a large kitchen or need to make structural adjustments, the project will take longer than a basic renovation with only aesthetic changes.
In general, a kitchen remodel takes between six and twelve weeks to complete, not including the design and planning process.
Here’s a summary of a typical renovation timeline to give you a better idea of what to expect.
Design and planning
Good planning is the foundation of a successful kitchen renovation. Before meeting with your contractor to discuss how to make your dream kitchen a reality, you should have a clear vision and a budget in mind.
You and your contractor or designer will need to create a floor plan, an elevation plan, an electrical and plumbing plan, and other documents at this point. Appliances, fixtures, cabinets, flooring, and backsplashes must be chosen.
The planning and design stage usually takes 2 to 4 weeks.
Materials are being ordered.
Ordering should be planned for a month. You can order all of the items at once or spread them out depending on your budget. You can also schedule the delivery of your orders to coincide with the completion of your project.
Construction
It can take anywhere from a few weeks to a few months to complete construction. Here are the steps and a rough schedule for each:
- 2 to 1 week for demolition, framing, and dust protection
- 1 week for HVAC, plumbing, and electrical installation
- Insulation and drywall installation took two weeks.
- Flooring and cabinet installation takes 1 to 2 weeks.
- 1 week for countertop fabrication
- 1 week to install the countertops and appliances
- 2 weeks for painting and finishing
As previously said, depending on a variety of factors, the full process can take less or more time.
Here are some things you can take to avoid delays:
Choose and buy your appliances as soon as possible. Due to the reliance of cabinets and layout on appliances, changing them after the design plans are finalized or construction has begun may create significant delays
- To account for shipping delays and backorders, order your materials early.
- Apply for building permits as soon as possible.
- Have a clear and realistic budget in place from the start, with a 20% buffer for unanticipated costs.
- Try to stay away from distractions from the assignment, such as needing to work around your regular schedule. Plan to stay clear of the construction zone so that workers may get on with their task.
- Only work with a reputable and experienced contractor that has a track record of success. To ensure clear communication from the start, keep lines of contact open throughout the process.
Kitchen remodeling near me takes time, but if you and your contractor have a strong working relationship, you’ll be rewarded with a stunning new hub for your house. Contact us at (713) 930-0003 or a local contractor for more tips and information on How Long kitchen remodeling Takes.